SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 certification exam success is guaranteed in the first attempt without any failure is possible now with the best SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam dumps preparation material is designed by the professionals according to the needs of candidates who want to prepare for the SAP C_TPLM22_64 exam in a short time perfectly. The SAP C_TPLM22_64 exam dumps preparation material consists of the practice test software as well as PDF Q&A booklet that contain the most recent questions of SAP C_TPLM22_64 exam.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received?
Please choose the correct answer.
Response:

A. No project stock
B. Valuated project stock
C. Non-valuated project stock
D. Sales order project stock

Answer: C

Question: 22

Which types of networks store all the activity and material component costs at the network header level and behave in the same way as all other order categories?
Please choose the correct answer.
Response:

A. Order header networks
B. Order category networks
C. Assignment networks
D. Header assigned networks

Answer: D

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD