SAP Project Manager C_PM_71 certification exam success is guaranteed in the first attempt without any failure is possible now with the best SAP Certified Associate Project Manager C_PM_71 exam dumps preparation material is designed by the professionals according to the needs of candidates who want to prepare for the SAP C_PM_71 exam in a short time perfectly. The SAP C_PM_71 exam dumps preparation material consists of the practice test software as well as PDF Q&A booklet that contain the most recent questions of SAP C_PM_71 exam.

C_PM_71 exam questions, C_PM_71 PDF dumps; C_PM_71 exam dumps:: https://www.dumpsschool.com/C_PM_71-exam-dumps.html (94 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_PM_71 Dumps Exam Questions and Answers:

Version: 4.0
Question: 21

How can you access the ASAP 8 Roadmap?
Response:

A. SAP Service Marketplace
B. ASAP CD
C. SAP Partner Portal
D. SAP Help Portal

Answer: A

Question: 22

You are in the early stage of setting up an implementation project. What key components of project governance do you need to establish and agree with your project sponsor?
There are 2 correct answers to this question.
Response:

A. SAP Solution Manager system
B. Roles and responsibilities
C. Project schedule
D. Project organizational structure

Answer: BD

Question: 23

New Updated C_PM_71 Exam Questions C_PM_71 PDF dumps C_PM_71 practice exam dumps: https://www.dumpsschool.com/C_PM_71-exam-dumps.html

Which of the following must be included in the project charter?
Please choose the correct answer.
Response:

A. Project organizational chart
B. Project objectives and benefits
C. Project team training plan
D. Solution architecture diagram

Answer: B

Question: 24

Which of the following tasks need to be completed successfully to complete the production cutover deliverable?
There are 3 correct answers to this question.
Response:

A. Obtain Production Data Sign-off
B. Finalize Cutover plan
C. Conduct Project Management Review Service
D. Execute Multiple cutover Simulations
E. Preform people readiness assessment

Answer: BDE

Question: 25

Which Accelerators from the ASAP Roadmap do you leverage to complete the Phase Closure and Sign-off Phase Deliverables?
There are 2 correct answers to this question.
Response:

A. Project Quality Gate Scorecard Template
B. Project Setup Check list Sample
C. Phase Closure Report Template
D. On-Boarding Template

Answer: AC

Question: 26

In the Project Preparation phase Data Quality Analysis in initiated.
Which Accelerators in the Data Migration Approach and Strategy deliverable is used to capture the baseline for Data Quality?
Response:

A. Data Migration Workshop Findings Template
B. Data Migration Approach and Strategy Template
C. Data Audit Results Report Template
D. Data Migration Scoping Questionnaire Template

Answer: C